Post by 49wjd » Wed Dec 06, 2017 8:32 pm

My basement project required relocation of the rough-in drains placed by the builder, and thus a section of the concrete floor was removed. That section of concrete contained the intersection of two perpendicular control joints. How important is reconstruction of the control joints when the new concrete is poured?

Factors that may (or may not) be relevant:
- house was built 3 years ago, foundation and basement floor poured about the same time
- radon levels were elevated and mitigation system is in place
- the new concrete will be covered by combination of shower base, porcelain tile, walls, and carpet
- house is built on expansive soils


User avatar
Shannon
Posts: 9087
Joined: Fri Nov 25, 2011 11:58 pm
Location: Canada
Contact:

Re: basement floor - control joints

Post by Shannon » Wed Dec 06, 2017 9:30 pm

The control joint lines really are not needed in the new portions. IMO. Everything will be covered with flooring so it should not be important.
If you've found our videos or website information helpful, please considering pledging us on Patreon

User avatar
A. Spruce
Posts: 2650
Joined: Tue Aug 16, 2016 5:23 pm
Location: California, USA

Re: basement floor - control joints

Post by A. Spruce » Wed Dec 06, 2017 11:07 pm

Control joints are used to control how large slabs crack. In this instance, pouring new concrete against old concrete gives you that same control.

The only thing you're probably going to want to consider will be to use an isolation membrane between the concrete and your tile, this way any movement in the slabs won't crack the tile.
If you've found our videos, forum, and answers helpful, consider making a small donation to help us keep the lights on and the help flowing. 8-)